Refurbishment work on Theodor-Heuss-Platz: construction phases and traffic restrictions

Transparenz: Redaktionell erstellt und geprüft.
Veröffentlicht am

Refurbishment work on the road in the confluence area of ​​Masurenallee is carried out at Theodor-Heuss-Platz in Berlin. The construction measures commissioned by the Charlottenburg-Wilmersdorf street and green area office include three construction phases. During the construction work, the bus stop U Theodor-Heuss-Platz south is moved forward, and cycling is diverted to the sidewalk. In the first construction phase, three of the four traces of the Masurenallee confluence area are blocked for four days. In the second section, the concrete field of the bus stop and the remaining traces are renewed. During the third construction phase, which lasts until the concrete is completely hardened, the condition remains largely unchanged. The construction site then becomes complete ...

Refurbishment work on Theodor-Heuss-Platz: construction phases and traffic restrictions

Am Theodor-Heuss-Platz in Berlin is carried out for renovation work on the road in the confluence area of ​​Masurenallee. The construction measures commissioned by the Charlottenburg-Wilmersdorf street and green area office include three construction phases. During the construction work, the bus stop U Theodor-Heuss-Platz south is moved forward, and cycling is redirected to the sidewalk.

In the first construction phase, three of the four traces of the Masurenallee confluence area are blocked for four days. In the second section, the concrete field of the bus stop and the remaining traces are renewed. During the third construction phase, which lasts until the concrete is completely hardened, the condition remains largely unchanged. The construction site is then completely cleared.

The construction work takes place on the following periods:
- 1. BA: April 22, 2024 to April 25, 2024
- 2nd BA: April 25, 2024 to April 30, 2024
- 3rd BA: April 30, 2024 to May 7, 2024

During the construction period, there will be restrictions in the southern area of ​​Theodor-Heuss-Platz. Bus traffic is diverted from the Jafféstrasse to the side lane of Heerstrasse, which also affects the Württembergallee stop.

The construction work is financed from federal funds and are planned in coordination with the road traffic authority and traffic control Berlin. The Charlottenburg-Wilmersdorf civil engineering office and the construction company are working to complete the work quickly and efficiently.



Source: www.berlin.de